2951 days ago
A process that was meant to take just four weeks has taken four months but heck this is Greece we are talking about, the Scotland of the South. A third of adults in Greece work for the Government but nothing ever gets done. But today we have learned that the Architects Council has okayed our plans to redevelop the Greek Hovel. Phew.
3105 days ago
The forestry permit was meant to take three months but took seven. Our architects - who one imagines are not exactly rushed off their feet with new projects - then took another two and a half months getting ready plans which were meant to have been ready when Forestry came through. But last week I was told that we will submit for a Building permit next week.
No-one answered my emails since then and so
3130 days ago
It was meant to take three months but took closer to a year but who cares? We now have a forestry permit received for the Greek Hovel. It seems that I failed to (illegally) cut down a few wild olive trees but most of my good works of the summer before last in clearing 2000 square metres of frigana have not been noticed and so we can now.....